Statutory Instrument 1989 No. 2315

The A5/A49 Trunk Roads (Shrewsbury Bypass and Improvements) (Temporary Bridge over the River Severn at Uffington, Shrewsbury) Order 1989

(The document as of February, 2008)

-- Back --

STATUTORY INSTRUMENTS

1989 No. 2315

HIGHWAYS, ENGLAND AND WALES

The A5/A49 Trunk Roads (Shrewsbury Bypass and Improvements) (Temporary Bridge over the River Severn at Uffington, Shrewsbury) Order 1989

Made7th December 1989
Coming into force5th January 1990

    The Secretary of State for Transport makes this Order in exercise of powers conferred by section 106 of the Highways Act 1980[1], and now vested in him[2], and of all other enabling powers:
        1.    The Secretary of State is authorised to construct the temporary bridge specified in the Schedule to this Order for the purposes of transporting spoil, building materials and machinery in connection with construction of the new trunk road and the River Severn crossing at Uffington, Shrewsbury.
        2.    In this Order-
       (i) "the new trunk road" means the new trunk road to be constructed by the Secretary of State in pursuance of the (A5) London-Holyhead Trunk Road and Slip Roads and the(A49) Newport-Shrewsbury-Whitchurch-Warrington Trunk Road (A5/A49) Shrewsbury By-Pass and Improvements) Order 1985[3] and the (A5) London-Holyhead Trunk Road and Slip Roads and the (A49) Newport-Shrews-bury-Whitchurch-Warrington Trunk Road (A5/A49 Shrewsbury By-Pass and Improvements) (Overley Hill) (No. 2) Order 1985[4];
       (ii) "the River Severn Crossing" means the bridge to be constructed by the Secretary of State over the River Severn at Uffington in pursuance of the (A5) London-Holyhead Trunk Road and Slip Roads and the (A49) Newport-Shrews-bury-Whitchurch-Warrington Trunk Road (A5/A49 Shrewsbury By-Pass and Improvements) Order 1985.
        3.    This Order shall come into force on 5th January 1990 and may be cited as the A5/A49 Trunk Roads (Shrewsbury Bypass and Improvements) (Temporary Bridge over the River Severn at Uffington, Shrewsbury) Order 1989.


Signed by authority of the Secretary of State

D. R. Ritchie

Regional Director West Midlands Region Department of Transport

7th December 1989





Notes:

[1] 1980 c. 66.

[2] S.I. 1981/238.

[3] S.I. 1985/1703.

[4] S.I. 1985/1704.

-- Back --